clean fruit processing plant machine
Uncooked substance Clean fruits
End merchandise Distinct AJC/apple juice concentrate
Brix70~72 in aseptic luggage
Hourly processing capacity up to 5 MTPH of raw fresh apples
Day-to-day processing capacity up to a hundred and twenty MT/day, based mostly on a few shifts
Processing period 60 days (or more)
Total processing capacity 7200 MT/yr
One power juice Brix Average Brix 12, min. 10. and max. Brix 15.
B/A, Acidity, and many others. TBC
Common juice yield 90%, with double extracting.TBC and enzymation
Squander materials Peel and extra pulp
Evaporator juice inlet 4000 Kg/hr 12. °Brix
Evaporated capacity up to 4000 L/hr (very first result 80 °C)
Concentrate outlet capacity up to 685 Kg/hr (in=12,°Brix / out=70 °Brix)
Focus outlet Brix 70 to 72 °Brix (adjustable)
Packaging Aseptic luggage
Item CZPT Name QTY
A FRESH APPLE PRE-Handling SECTION
A1 Fresh apple obtaining pool 1
A2 CZPT flume 1
A3 Bucket elevator with pump 1
A4 Air-blowing & washing channel 1
A5 Fruit washing and sorting combiner 1
A6 Waste fruit discharge conveyor 2
A7 Drinking water filtration & recycling device for product A 1
B EXTRACTION SECTION
B1 HL bucket elevator 1
B2 Hammer chopper
(Equipped with some knives and rotors) 1
B3 Chopping system one
B4 Buffer tank 1
B5 Screw pumps 2
B6 Continuous belt press/1st phase
(with 1 set of belt as standby) 1
B7 Screw conveyor 1
B8 Screw pump 1
B9 Receiving tank one
B10 Screw pump 1
B11 Steady belt push/2nd stage
(with 1 set of belt as standby) one
B12 Functioning platform for pressing 1
B13 Peels & seeds screw conveyor 1
B14 Balance tank for uncooked juice 1
B15 Integrated upstream management system 1
C ENZYMOLATION & FILTRATION SECTION
C1 Plate heat exchanger 1
C2 Enzymation tanks(1000L,double-layer) four
C3 Enzyme dosing unit one
C4 Procedure platform one
C5 Centrifuge pump 1
C6 Disk centrifuge separator 1
C7 Buffer tank 1
C8 Ultrafiltration Unit 1
C9 Sectional management program one
D CONCENTRATION SECTION
D1 Buffer tank two
D2 Tri-impact slipping movie vacuum evaporator 1
D3 Manage technique for item C 1
D4 Procedure platform 1
D5 Screw pump 2
E UHT STERILIZATION SECTION
E1 balance tank 1
E2 Plate UHT sterilizer 1
E3 Control system 1
F SINGLE-HEAD ASEPTIC FILLING SECTION
F1 Single-head aseptic filler 1
F2 Drum infeed and exit rollers one
F3 Label printing station 1
F4 Manage system one
G TIN CAN FILLING SECTION
G1 tin can washer one
G2 Tin can filling and seaming monobloc for two hundred~600g tin cans one
G3 constant pasteurizing & cooling method 1
G4 air dryer 1
G5 Labeling machinery
G6 ink coder(Linx) 1
G7 best chain conveying system 1
Welcome to inquiry: Guo: Tel:18516198359 we will reply you inside 2 hours.